By: Jacques Morisset--STORY HIGHLIGHTS
- The Dar es Salaam Port provides a gateway for 90% of Tanzanian trade and is also the access route to six landlocked countries including Malawi, Zambia, Burundi, Rwanda, and Uganda, and Eastern DRC
- The 3rd Tanzania Economic Update reports that inefficiencies at the Dar es Salaam Port are costing consumers more time and money than other comparable ports
- Delays at the port can last up to 20 days for everyday items such as diapers and milk to emergency medical supplies and medicines
DAR ES SALAAM, May 21, 2013 -- Ordinary shoppers in Dar es Salaam would be familiar with the story: "Tafadhali mama nipe muda kidogo, mzigo wangu bado uko bandarini,ukitoka nitakupigia haraka, tafadhali mama naomba univumilie, hii kwa kweli itakua wiki inayokuja…"
That would be a Dar es Salaam store owner pleading with an agitated customer over an item that just happens to be out of stock. It is the customer's second, maybe third time, to be told this. ("Mama, give me just a little time, my new stock is still stuck at the Port but as soon as it comes out, I shall call you. Please bear with me; it will be within the coming week for sure!")
This situation could happen with everything from popular brands of diapers, milk, and sanitary products to medicines and medical supplies, with shortages extending for several weeks or months. On the medical front, where the shortage could easily mean a life-or-death situation, hiring a courier becomes an option though not an automatic one for many ordinary patients.
The Tanzania Economic Update (TEU), a biannual series on the country's economy, shows that container vessels transporting imported merchandise were on average queuing for 10 days to be able to berth at the Dar es Salaam Port. It could also take up to an additional 10 days to unload the merchandise, clear it and transport it. By comparison, container vessels at the Port of Mombasa, the largest in East Africa, took less than a day to berth in 2012, and three-to-four days to unload, clear and transport merchandise. The international standard is two days.While officials at the Port of Mombasa charge simple flat rates, Dar es Salaam Port fees are based on the value of the merchandise, which could account for why fees are 74% higher in Dar es Salaam. According to the report, the cost of these inefficiencies translates into a tariff of 22% on container imports and about five percent on bulk imports, and financial losses for shippers and shipping companies.
"These costs are in general passed on to consumers," said Jacques Morisset, lead economist for Tanzania, Uganda and Burundi and author of the report.
According to the report, an average household would save US$147 a year or 8.5% of total expenditures if the Dar es Salaam Port were as efficient as the Port of Mombasa.
Tracking the Losses
Not only does the Dar es Salaam port provide a gateway for 90% of Tanzanian trade, it is also the access route to six landlocked countries including Malawi, Zambia, Burundi, Rwanda, and Uganda, as well as Eastern DRC. The TEU also highlights the costs to both domestic and international level stakeholders as a result of the port's inefficiency:
- 37% – the equivalent tariff on total energy imports which constitute 35.5% of total imports, as a result of long delays
- US$252 million – the losses incurred by shippers and shipping companies in total annual anchorage costs, as a result of long delays
- US$17.4 per ton – the cost that an importer of merchandise worth US$1,358 is willing to pay in bribes to speed up processes
- US$1,759 million – the total welfare loss to the Tanzanian economy as a result of the port's inefficiency
- US$830 million – the total welfare loss to the economies of neighboring countries that are using the port of Dar es Salaam
- US$157 million – lost revenues for government agencies such as Tanzania Ports Authority (TPA) and the Tanzania Revenue Authority (TRA)
Why Reforms are Imperative
The TEU identifies several causes of Port inefficiencies, including the failure to invest in appropriate infrastructure, corruption and those who benefit from it, a general lack of awareness of the costs by stakeholders and the unequal distribution of those costs.
Along with the KPMG audit firm, the World Bank conducted a survey of 100 mid-sized Tanzania businesses. Sixty-two percent of respondents said that Port ineffectiveness harmed their businesses slightly while 20% said it harmed them extremely.
Nevertheless, 39% of the firms also reported a sense of improvement in the port's operations in 2013, which could be the result of some recent changes. The government has taken steps to make improvements, including management and personnel changes, providing higher tech equipment such as cranes and scanners, and implementing a banking system for all transactions.
The TEU refers to this "political appetite for change" as an opportunity to encourage government authorities to "design and implement strategies that effectively facilitate the increased volume of trade and its changing nature through the development of an investment plan which makes TPA fully operational."
Unlike many reforms that cost a lot of money, the report highlights five cost-effective recommendations to increase Port performance. These include increasing consumer awareness of inefficiency costs, reducing corruption, motivating reformers and improving coordination.
With these actions, Tanzania could potentially accelerate its economic prospects to achieve additional revenues of up to US$1.8 billion (Sh2.93 trillion) per year, or a seven percent increase in its gross domestic product, while neighboring economies stand to gain US$830 million.
Send Emails to wanabidii@googlegroups.com
Kujiondoa Tuma Email kwenda
wanabidii+unsubscribe@googlegroups.com Utapata Email ya kudhibitisha ukishatuma
Disclaimer:
Everyone posting to this Forum bears the sole responsibility for any legal consequences of his or her postings, and hence statements and facts must be presented responsibly. Your continued membership signifies that you agree to this disclaimer and pledge to abide by our Rules and Guidelines.
---
You received this message because you are subscribed to the Google Groups "Wanabidii" group.
To unsubscribe from this group and stop receiving emails from it, send an email to wanabidii+unsubscribe@googlegroups.com.
For more options, visit https://groups.google.com/groups/opt_out.
Send Emails to wanabidii@googlegroups.com
Kujiondoa Tuma Email kwenda
wanabidii+unsubscribe@googlegroups.com Utapata Email ya kudhibitisha ukishatuma
Disclaimer:
Everyone posting to this Forum bears the sole responsibility for any legal consequences of his or her postings, and hence statements and facts must be presented responsibly. Your continued membership signifies that you agree to this disclaimer and pledge to abide by our Rules and Guidelines.
---
You received this message because you are subscribed to the Google Groups "Wanabidii" group.
To unsubscribe from this group and stop receiving emails from it, send an email to wanabidii+unsubscribe@googlegroups.com.
For more options, visit https://groups.google.com/groups/opt_out.
0 comments:
Post a Comment