Asset Management
I noted that NSSF spent a sum of Shs. 234.1 billion in the
construction of some of the buildings of the University of
Dodoma (UDOM), under contract terms of Design, Build, Own
and Transfer after 10 years. Other Funds PSPF, LAPF, NHIF
and PPF spent a total of Shs.181.3 billion in construction of
buildings of the Dodoma University under the same terms of
contract. The constructed buildings are neither in the books
of University of Dodoma nor in the books of the Pension
Funds. This has been caused by different understanding of
the parties concerned. Pension Funds understand that
amount used to construct the buildings was the loan to the
Government while on the part of Government understands
was an investment of the Pension Funds.
Further, I noted non performing loans with a sum of Shs.91.7
billion and USD 9.65 million. The amount was loaned for the
constructions of Bunge Hall, Police houses and Machinga
Complex at Dar es Salaam City Council. Others were used to
finance, General Tyre East Africa Ltd, Kiwira Power Coal
Mining, Dar es Salaam Cement Company, Continental Venture
Limited, Kagera Sugar Co. Limited and Medtch Industrial Co.
Limited under the Government guarantee.
The non performance of these loans guaranteed by the
Government exposes the Pension Funds to high risk of losing
the members' funds and therefore jeopardising the ability of
further re-investing. In addition, I have noted with concern
on the non repayment of the loaned funds from the Pension
Funds and the non payment by the Government of the
guaranteed amounts due to the failure of those who have
been guaranteed as per the loans agreements and which is
contrary to the loans and Guarantees Act of 1974.